Current roads program

Works continuing through 2019/20

In the current financial year $55million will be invested in renewal and rehabilitation works on our roads and bridges, and another $15million on maintenance works. That’s $777 for every MidCoast resident, compared to as little as $30 per resident in some Sydney suburbs.

The table below indicates projects, locations and timings in this year’s Capital Works program. Those highlighted in orange are funded through the $100 million Road Upgrade Package. Over and above these projects, you’ll also see our crews out across the region every day, undertaking maintenance works such as pothole patching, roadside slashing and gravel resheeting.

Note – This table is a condensed version of a more detailed capital works program that is updated and presented monthly at our council meetings. You can view the latest version by downloading it from the attachments on our Council Meetings web page. You can also view what we have completed over the past 12 months here.

Projects in blue are completed

Projects in green are underway or scheduled to commence

Projects in orange are funded through the $100 million Road Upgrade Package

Project  Locality Scope of Works Schedule

 Carryover Projects from FY18/19

 The Lakes Way (north)  Rainbow Flat   Blackhead Road to Chelmsbrook Road  April - June 20
 Manning Point Rd  Mitchells Island  Road rehabilitation - 2.5km  Complete
 Manning Point Rd  Mitchells Island  Road rehabilitation - 480m  Complete
 Callaghans Creek Bridge  Cundle Flat  Replacement of timber bridge, Callaghans Creek Rd  Complete
 Manning St (High St / Cornwall St)  Taree  250m length   Complete
 Farquhar (Bent St / Primrose St and Primrose St / Queen St)  Wingham  450m length  May - August 20
 Queen Street  Gloucester  440m length - Church to Ravenshaw  end-Jan - Aug 20
 Primrose St (Canget St to Farquhar St, to Isabella St)  Wingham  360m length  April - July 20
 Victoria St (Commerce St / Flett St)  Taree  300m length  Complete
 Upper Myall Rd  Upper Myall  1.5km length, seal of unsealed road (segment 10,25,30)  Complete
 Milbai Creek Bridge  Tinonee  Replacement of timber bridge, Tinonee Road  Complete
 Little Cedar Party Creek Bridge  Cedar Party  Replacement of timber bridge on Comboyne Road  Jan - June 20
 Possum Brush Road Bridge No 2 (also known as Bungwahl Bridge)  Possum Brush  Replacement of timber bridge on Possum Brush Road   Oct 19 - May 20
 Kundle Creek Bridge  Bucca Wauka  Replacement of timber bridge on Wallanbah Road  Jan - May 20 
 Cedar Tree Creek Bridge - Willina Road  Bunyah  Replacement of timber bridge on Willlina Road  Complete
 Emu Creek Bridge  Bulahdelah  Replacement of timber bridge on Booral Road  Oct 19 - May 20
 Burrell Creek Bridge  Burrell Creek  Replacement of timber bridge on Kimbriki Road  Oct 19 - May 20
 McQueen Bridge  Number One  Replacement of timber bridge, Nowendoc Road  TBC
 Diamond Bridge  Wingham  Replacement of timber bridge, Mooral Creek Road    Jan - May 20
 Reltons Bridge  Wards River  Replacement of timber bridge, Johnsons Creek Road  May - Sept 20
 Wards River Bridge  Weismantels  Replacement of timber bridge, Terreel Road  March - Aug 20
 Gunyah Causeway  Bobin  Reconstruct concrete causeway   TBC
 Denva Rd  Taree South  Segment 10, 500m   Complete
 The Bucketts Way, LP02, Manchester St - Peg Leg Creek  Tinonee  1,430m segment    Complete
 Cedar Party Rd   Cedar Party  1,140m length (segments 120,140,150)   Complete
 Coralville Rd  Coralville  400m length (segment 10)  Complete
 Boating Now - Boat Ramp, Cundletown  Cundletown  Formalising and sealing parking areas  Complete
 Avalon Rd (MR 90 / Middle of bend - No 373)  Krambach  630m length   Complete
 MR 7719 Thunderbolts Way - Seg 150-160  Barrington  1,460m length  Complete

 Urban Rehabilitation

     
 Old Bar Road  Old Bar  Sheppard Street to David Street (segments 230 & 250)  28 April - mid-July 20
 Beach Street  Harrington  Wards Gully Bridge (Harrington Rd Bridge) to Pacific Place (segment 40)  mid-April - end-May 20 
 Cornwall Street, Marathon Street, Olympia Street  Taree   Whitbread St to Cornwall (seg 20), Olympia (seg 10), Marathon (seg 10)  May - June 20
 Muldoon Street  Taree  Railway crossing to Kanangra Drive (segs 10, 20, 30, 40, 50, 60, 70)  Commencing April 20
 Helen Street  Forster  Little Street to Macintosh Street (seg 10)  Complete
 Maxwell Street  Tea Gardens   Myall to Witt (seg 20)   Commencing March 20
 Motum Avenue  Tea Gardens   Myall Street to Jacob Street (seg 10)   Complete
 Witt Street  Tea Gardens  Hough to Ogden (seg 15)   TBC
 Queen Street (stage 3)  Gloucester    TBC  TBC 
 Blackhead Road  Hallidays Point   Diamond Beach Road to start K&G on LHS (segs 120 and 130)   Commencing June 20

 Urban Construction

     
       
     

State Rd RMCC Works

     
 Failford Road  Failford   Pavement rehabilitation, 675m length (seg 535)  Currently being designed 
 Reseal program  Various  Transport for NSW identified segments to be resealed  Ongoing
 Drainage improvement program  TBA     TBC
 Mark Street roundabout resurfacing  Forster   Resurfacing of roundabout and approaches, Macintosh / Mark Street intersection  March - April 20
 Heavy patch program  Various   Annual program   Ongoing 

 Other Internal Council Works

     
 Dredging Program - Harrington  Harrington  Dredging in accordance with grant funding and licence  Complete
 Dredging Program - Lower Myall  Lower Myall  Dredging in accordance with grant funding and licence  June - Sept 20
 Dredging Program - Tuncurry  Tuncurry  Dredging in accordance with grant funding and licence  TBA - Await licence approval
 Dredging Program - Farquhar  Farquhar   Dredging in accordance with grant funding and licence  TBA - Await licence approval
 Tallwoods roundabout  Tallwoods Village  Roundabout construction, int. Blackhead Rd & Tallwoods Blvd  Lighting installation April
 Grangewood Avenue  Tallwoods Village   Reconstruction of flood damaged culvert  Complete

Rural Rehabilitation

     
 Waukivory Road  Gloucester  Segments 10 and 20  Complete
 Bulga Road  Marlee  Segments 120 and 130   In progress
 Hannam Vale Road  Moorland   Segments 70, 80, 90, 100 and 110   April - May 20 
 Nowendoc Road  Mount George   Segments 330, 340, 350  April - May 20
 Markwell Road  Bulahdelah   Segments 20 and 22   May - July 20

 Rural Construction

     
 The Branch Lane    Seal extension  March - April 20 
 Wattley Hill Road    Seal extension  April - May 20
 Willina Road    Seal extension  Complete
 Upper Myall Road    Seal extension   Next FY

Regional Rehabilitation

     
 Avalon Road  Krambach  Fire Station Road to Paterson Lane (segments 330 and 360) March - July 20
 Old Bar Road  Old Bar  Stage 2 - Pampoolah to cemetery  Q4 2019/20
 Old Bar Road  Old Bar   Old Bar Road and Saltwater Road intersection (Stage 3)  mid-March - mid-June 20
 The Lakes Way  Forster  Tea Tree intersection to Sweet Pea Road (segment 350)  TBC
 The Bucketts Way  Craven  1.5km length. Overtaking lane  Complete
 The Bucketts Way  Limeburners Creek  1.25km length. Reconstruction, widening and overtaking lane  May 19 - Mar 20
 The Lakes Way  Tarbuck Bay  Tarbuck Bay Road (segment 196)  Complete
 The Lakes Way  Boolambyte   Segments 40, 41, 42 - approx. 1.15km length  Next FY
 The Lakes Way  Mayers Flat   Segments 80, 82 - approx. 1.3km length  Feb - June 20 
 Stroud Hill Road  Nooroo   Segments 71, 73, 75 - aoprox. 1.18km length  Next FY
 Wingham Road  Kolodong  Cedar Party Rd to Hargreaves incl. roundabout and realignment (segs 450, 550)   First stage commencing May 20
 Isabella Street  Wingham  Design of segments 370 to 400   Next FY 
 Gloucester Road  Wingham  From Dollys Flat Road intersection, 1.3km  Late February - end June 20
 Thunderbolts Way - Project No. 01  Giro  Segments 525 to 545, pavement rehabilitation and truck arrestor  TBC
 Thunderbolts Way - Project No. 04  Carsons Lookout  Segments 600 to 610, pavement rehabilitation  Next FY
 Thunderbolts Way - Project No. 06  Tibbuc  Segments 310 to 320, pavement rehabilitation  Next FY
 Argyle Street Barrington (Thunderbolts Way - Project No. 12)  Barrington  Segment 105, pavement rehabilitation  mid-April - July 20
 The Bucketts Way Stroud Road  Stroud Road   Intersection with Reidsdale Rd, Segment 280    Commencing July 20
 The Bucketts Way Stroud  Stroud   South intersection with Stroud Hill Road, segments 230 and 234  Commencing Oct 20
 The Bucketts Way Gloucester  Forbesdale  South Gloucester village, segments 605, 610, 615, 620, 625, and 630  Commencing May 20
 The Bucketts Way Tinonee  Tinonee  Design only of segments 210, 220, 230, 240 - extend to end of segment  Currently being designed
 The Bucketts Way, second stage of LP02  Tinonee      Commencing June 20
 Manning River Drive  Taree  AC rehabilitation, segment 300B  TBC 
 Manning River Drive  Taree South  Design only of dual lane, segments 80 to 90   TBC 

 Bridge Renewals

     
 Deep Creek Bridge (Wallamba River)  Wherrol Flat   Wherrol Flat Road, road segment 110  TBC 
 Browns Creek Bridge  Bunyah Road   Bunyah Road, road segment 60   TBC 
 Ashlea Bridge  Wherrol Flat  Wherrol Flat Road, road segment 40  TBC 
 Bundacree Creek Bridge  Minimbah Road  Minimbah Road, road segment 20  TBC
 Sheathers Bridge  Hannam Vale  Hannam Vale Road, road segment 310  TBC
 The Falls Bridge  Glenwarrin Road  Glenwarrin Road Elands, road segment 70  TBC
 Teatree Creek Bridge  Wattley Hill Road  West of Barbies Road, road segment 45  TBC

 Culvert Renewals

     
       

 Concrete Works

     
     

Stormwater

     
 Forster Keys re-lining  Forster Location TBC  TBC
 North Arm Cove drainage strategy project  North Arm Cove    TBC

Waste Projects

     
 Tea Gardens Weighbridge  Tea Gardens  Installation of new weighbridge to meet reporting requirements  Late-April - June
 Minimbah Landfill  Minimbah  Completion of construction to enable activation of landfill  TBC